| Industry |
Name of Project |
Date |
System |
Capacity (m³/hr) |
Q'ty |
| LNG Plant |
Pyungtaek LNG Terminal |
1993 |
Trash Rack |
|
2 |
| LNG Plant |
Pyungtaek LNG Terminal |
1993 |
Trash Rack |
|
1 |
| Power Plant |
Kwangyang Steel Traveling Water Screen |
1991 |
Travelling Water Screen |
11,000 |
5 |
| Power Plant |
Kwangyang Steel Traveling Water Screen |
1991 |
Moving Bar Screen |
11,000 |
5 |
| Power Plant |
Kwangyang Steel Traveling Water Screen |
1989 |
Moving Bar Screen |
11,000 |
5 |
| Power Plant |
Kwangyang Steel Traveling Water Screen |
1989 |
Travelling Water Screen |
11,000 |
5 |
| Power Plant |
Kwangyang Steel Traveling Water Screen |
1989 |
Stop Gate |
|
2 |
| Power Plant |
Pohang Steel Traveling Water Screen |
1988 |
Travelling Water Screen |
9,000 |
3 |
| Power Plant |
Pohang Steel Traveling Water Screen |
1988 |
Moving Bar Screen |
11,000 |
3 |
| Power Plant |
Pohang Steel Traveling Water Screen |
1988 |
Stop Gate |
|
4 |