| Industry |
Name of Project |
Date |
Capacity (m³/day) |
Process |
Work Scope |
| Oil&Gas/Chemistry |
Yosu Storage Base Industrial Wastewater Treatment Facilities |
2007 |
2,600 |
Physical-chemical/Standard Activated Sludge |
EPC |
| Oil&Gas/Chemistry |
SK ENERGY BDO Project Raw Water System |
2007 |
2,880 |
Clarifier |
EPC |
| Oil&Gas/Chemistry |
SK CORP. NEW FCC PJ. Clarifier |
2007 |
1,680 |
Clarifier |
EPC |
| Iron/Steel |
Kwangyang 2, 3 Continuous Casting Machine Revamping Facility & Water Treatment |
2007 |
14,400 |
Heat Exchanger + Ion Exchanger |
EP/SV |
| Iron/Steel |
Kwangyang 2 3 Casting 2, Continuous Machine Revamping Facility & Water Treatment |
2007 |
200 |
Conventional/Dewatering/ Chemical dosing |
EP/SV |
| Iron/Steel |
POSCO NO.1 Hot Rolling Mill BH-COOLING |
2007 |
11,500 |
Heat Exchanger + Ion Exchanger |
EP/SV |
| Iron/Steel |
POSCO NO.1 Hot Rolling Mill BH-COOLING (Cooling Water & Wastewater) |
2007 |
150 |
Heat Exchanger + Ion Exchanger |
EP/SV |
| Reuse |
Waegwan sewer reuse system |
2007 |
10,000 |
UF+AC |
EP |
| Other Industry |
POSCO Extension |
2007 |
0.3km |
Vacuum Transfer System |
EP |
| Power |
Finex Power Plant Wastewater Treatment |
2006 |
1,400 |
Physical-Chemical |
EP/SV |