| Industry |
Name of Project |
Date |
Capacity (m³/day) |
Process |
Work Scope |
| Municipal |
Jeongseon Imgye Water Treatment NF process |
2008 |
1,500 |
NF |
EP |
| Municipal |
Goyang Wonnueng Sewage Treatment Plant |
2008 |
80,000 |
CSBR |
EPC |
| Power |
Boryeong #1~2 Thermal Power Plant Condensate Treatment System |
2008 |
32,160 |
Physical-Chemical |
EPC |
| Microelectronics |
Samsung LCD Water Treatment #3-1 |
2008 |
35,000 |
UF |
EP |
| Microelectronics |
Samsung LCD Wastewater reuse system |
2008 |
1,000 |
RO |
EP |
| Microelectronics |
Samsung LCD Wastewater reuse system #3-2 |
2008 |
1,000 |
AC+RO |
EP |
| Microelectronics |
Samsung electronics Giheung Pretreatment Demineralization System #K2 |
2008 |
70,000 |
UF |
EP |
| Municipal |
Goyang Byukje & ilsan Sewage Treatment Facilities |
2007 |
30,000 |
CSBR |
EPC |
| Oil&Gas/Chemistry |
Yosu Storage Base Industrial Wastewater Treatment Facilities |
2007 |
2,600 |
Physical-chemical/Standard Activated Sludge |
EPC |
| Oil&Gas/Chemistry |
SK ENERGY BDO Project Raw Water System |
2007 |
2,880 |
Clarifier |
EPC |